The Bishnumati Corridor road from New Bus Park to Kuleshwor in Kathmandu Metropolitan City has been asphalted.
The High-powered Bagmati Civilisation Integrated Committee has started works on construction of wall and on tarmacking the road along the side of the Bishnumati River.
The CM-PR JV Construction Service, which has the responsibility of repairing and asphalting the road from New Bus Park to Kuleshwor, has been vigorously pursuing the work of constructing the wall and tarmacking the 3.5 kilometres road.
Engineer of the consulting company, Maheshwar Khadka said the target is to complete the two projects within May this year. So far the tarmacking works have been completed on one kilometre from the bus park to Balaju and an additional 500 metres road in Shovabhagawati area.
The High-powered Bagmati Civilisation Integrated Committee will invest Rs 134 million 925 thousand 546 for the construction of the two projects.
There will be four underpasses on the corridor road — an underpass each at New Bus Park, Shovabhagawati, Dallu and Kuleshwor.