Friday Nov 22, 2024
Friday Nov 22, 2024

NEA incurring daily loss equivalent to Rs 40m due to surplus power: ED Ghising


Nepalnews
2021 Sep 12, 16:09, Kathmandu
This undated image shows the office of Nepal Electricity Authority in Ratnapark, Kathmandu.

With the power generated from Upper Tamakoshi Hydro Power Project getting connected to the national grid, around 400 MW of (surplus) electricity has remained unconsumed in the night.

The reserve electricity in a day is 200 MW. There was a time when the country was struggling for a single unit of power. The power distributing companies are facing more power surplus during the monsoon.

Nepal Electricity Authority (NEA) executive director Kulman Ghising said with the Upper Tamakoshi being connected to the national grid, the country has become self-sufficient in electricity.

A large volume of power going unused is not good. The NEA is incurring the daily loss equivalent to Rs 40 million due to surplus power, according to Kulman Ghising.

India could be the best market for surplus power, but no green light was achieved from India. As he said, during his recent visit to India, Ghising urged Indian officials for facilitating finding an accessible market for the surplus power from Nepal.

The NEA delegation discussed with the Indian side about exporting surplus power from here to India and importing power from India during the lean period.

NEA has proposed a mutual seasonal electricity exchange with Bihar State Power Holding Company Limited to utilise surplus power generated during monsoon from various hydropower projects including the 456-megawatt Upper Tamakoshi hydropower, said Ghising.

"A proposal has been made for Nepal to supply the surplus electricity to Bihar during monsoon and to bring it from Bihar during winter. In case of unequal amounts of electricity exchanged between Nepal and Bihar, its price will be fixed through an appropriate method," he said.

There has been an electricity agreement and exchange between Nepal and India since 1971.

So far, the NEA has reached the power purchase agreement with 346 hydropower projects to purchase 6,176 megawatts of electricity. Of them, 111 projects with 1,300 megawatts have been into operation.

Likewise, 136 with 3,034 megawatts are under construction. And other 99 with 1,841 megawatts are under the financial closing process, said the NEA

READ ALSO:

Nepal Electricity Authority Upper Tamakoshi Hydropower National Grid Kulman Ghising loss Surplus Power Bihar State Power Holding Company Limited india Bihar
Nepal's First Online News Portal
Published by Nepalnews Pvt Ltd
Editor: Raju Silwal
Information Department Registration No. 1505 / 076-77

Contact

Kathmandu, Nepal,


Newsroom
##

E-mail
[email protected]

Terms of Use Disclaimer
© NepalNews. 2021 All rights reserved. | Nepal's First News Portal